Property Refurbishment

3 bedroom semi-detached house.

 The property value was increased by 15%

& sold within 14 days.


The brief was to project manage the refurbishment of semi detached house prior to it being offered for sale.  There was a strict budget and time was tight to complete the project before the heart of the summer when the property would be looking its best.


Initial Observations

Whilst there were no serious areas of concern the property had been rented for a number of years and was starting to show its age.  In particular the kitchen and bathroom were extremely dated and in need of updating.  The carpets were also showing their age and some of the original fixtures and fittings were still in place.

Suggested works

Kitchen – Remove existing units and replace with a more modern kitchen
Kitchen – Remove existing appliances and update
Kitchen – Remove old tiles and re-plaster as required
Kitchen – Replace the existing back door and door fittings
Kitchen – Remove light fittings
Kitchen – Move/replace sockets & switches
Kitchen – Plaster ready for kitchen fit
Kitchen – Fit new floor
Kitchen – Paint/decorate
Kitchen – Replace door handles with chrome fittings

Pantry – Paint/decorate

Dining room – Repair/replace floor trim
Dining room – Repair/paint radiator covers
Dining room – Paint /decorate

Lounge – Repair/replace floor trim
Lounge – Repair/paint radiator covers
Lounge – Paint/decorate

Hall – Replace door handles with chrome fittings
Hall – Repair/paint radiator covers
Hall – Repair/replace floor trim
Hall – Paint/decorate

Stairs/Landing – Prepare and paint bannister to cover wood stain
Stairs/Landing – Replace carpet

Bedroom 1-3 – Replace door and fittings
Bedroom 1-3 – Replace carpet
Bedroom 1-3 – Paint/decorate

Bathroom – Remove existing suite
Bathroom – Re-Plaster
Bathroom – Tile 2 walls
Bathroom – Fit sub floor
Bathroom – Fit new flooring
Bathroom – Replace bathroom suit

Exterior

Clear the front and back garden
Clear the garden shed and out house

The finished project

All the above works were approved and work was completed within 3 weeks.  We managed the project on behalf of the owner within budget and within the given timescale.